Kitchen Worktop Replacement Preparation & Installation

(Blackburn, Pleckgate Area)

 

    This kitchen project in the Pleckgate area of Blackburn focused on preparing the space for new composite worktops. We began by removing the old worktops and carefully dismantling the plumbing to ensure everything could be reconnected cleanly once the new surfaces were installed.

     Because the customer was upgrading to a more powerful oven, we also created a dedicated access point for the electrician. This made it easier and more cost‑effective for them to run a new cable from the consumer unit to the oven tower.

The project was completed over two visits:
– Visit 1: Removal of the old worktops and full preparation for the composite installation.
– Visit 2: Installation of the sink and tap, plus reconnection of all plumbing once the new worktops were in place.

A clean, efficient upgrade that left the kitchen ready for years of use — and another solid project completed in the Blackburn Pleckgate area.